G and Z can do a work in 12 days (together). G can work alone in 20 days. so how many days it will take Z to finish the work alone?

answer will be 30 days. please show calculation

Respuesta :

Otras preguntas

How do you find the constant of variation when y=-(2/3) and x=3
can you tell me what is a mandolin?
What was vomitorium used for?
Which of the following is true regards to the Navigation Acts by the 18th century
what are the different periods under english literatureplease help me i need this now !!!! :)
Which of the following is true regards to the Navigation Acts by the 18th century
I really need help on this one...ASAP!I will try to answer your questions if you answer this soon asap! PLZZZZ!!!What would a equal if 4(a+12) was 32?
How much gas is there in 100cm3 of air?
why oxygen important in your body?
please help me write equation for each condition listed. 1- The vertical line that passes through ( –7, 4 ) 2- The horizontal line that passes through