p can do a piece of work in 50 days, q in 40 days and r in 30 days respectively. If r is assisted by p on one day and by q on the next day alternately then the work gets complete?
o 17 32/35 days
o 19 ⅔ days
o 16 31/37 days
o 16 31/37 days

Respuesta :

Otras preguntas

Answer these pleaseeee
CIRCLE THE INCORRECT PRONOUN SHIFT. REWRITE SENTENCE CORRECTLY. THE TEAM WON ITS CHAMPIONSHIP GAME LAST WEEK.
four million six percent of what number?
Name the property of real numbers illustrated by the equation 2+(√(5+7)=(2+√(5)+7 A: Distributive Property B: Associative Property Of Addition C: Associative Pr
What is the traditional interpretation of why the French Revolution started
please need help!!!!
In a more rational society, an ability to write would be of great help to her. but here, the only people who could read her writing would be those who might pun
explain two issues the colonists had with Great Britain
Give an example of a whole number that is not a natural number
How does stress effect your musculoskeletal system?