mimireds8679 mimireds8679
  • 26-03-2024
  • Mathematics
contestada

A can do a job in 3 days less time than B. A works at it alone for 4 days and then B takes over and completes it. If altogether 14 days were required to finish the job, then in how many days would each of them take alone to finish it?
A. 17 days, 20 days
B. 12 days, 15 days
C. 13 days, 16 days
D. None of these

Respuesta :

Otras preguntas

The Declaration of Independence is considered the first formal assertion by a people of their right to
What is the square root of 34 to the nearest 0.05
(√x+1/√x)^2find dy/ dx and substitute 2 in dy/ dx
what does the turgor pressure measure
Numbers between 231 and 239
the length of the bar of a hydro competition must always be 4.75 meters Express the measurement in meters explain your thinking include an equation with an expo
Who led the investigation that resulted in Alger Hiss being convicted of perjury?
Why is 8.8 a rational number?
Ms smith has 28 sixth graders and 35 seventh graders for math. If she wants to break the two grades into identical groups without any students left over how man
Circle Q has the central angle ∠AQB with a measure of 55°. Which of the following option is not true? AB is a minor arc the measure of AB=110 degrees The cente