The critical path on a project can change as the project progresses. select one:

a. true

b. false

Respuesta :

mirrorkitten
mirrorkitten mirrorkitten
  • 02-04-2019

The answer is True.

In project management, critical path refers to a sequence of stages that would require the smallest amount of time possible to bring a project to completion.

Critical path can change during a project since there might be circumstances during it which would lead certain activities to be finished longer or faster. Critical path can be determined by a specialized algorithm technique.

Answer Link

Otras preguntas

You are calculating payroll. your company has 45 employees who work 40 hours a week and earn $17/hour 14 employees each worked 6 hours of overtime at 50% above
What were the key points Bush wanted communicated to China?
As Section 3 of this chapter explains the Declaration was divided into four parts right down the first phrase of each of those four parts. That is the question
The sum of two integers is 6and the difference is 4 find the intergers
It takes for three gardeners 90 minutes to weed a garden. If the job is to be done in only 15 minutes, how many more gardeners need to be put on the jobs?
A(n) _____ is an organic compound that changes color in acid or bases.
Lee reads for 3/4 hour in the morning and 2/4 hour in the afternoon. how much longer does lee read in the morning than in the afternoon.
What is thegcf of 70 and 95?
Chinese peasants could now gain land by entering the military. True False
What does the word garter mean??