The person responsible for setting goals and schedules, monitoring work, motivating the team, and reporting progress to managers is the _____.

A. stakeholder
B. customer
C.sponsor
D.project manager

Respuesta :

anjaanladka anjaanladka
  • 23-04-2019

Answer:

D. Project Manager

Explanation:

Answer Link

Otras preguntas

Shear stress created the San Andreas Fault in Southern California. It is an example of a _____. normal fault reverse fault strike-slip fault syncline
Are the lines described by the equations y=x+2 and x+y=6 intersecting, coinciding, or parallel? Explain
I have a rectangle that is 2 1/2 feet long and 1 1/3 feet wide. What is the area of the rectangle? Please show work
The early arrival of spring in New Hampshire has no effect on wildlife.
________________ first proposed continental drift. A. J. Tuzo Wilson B. Harry Hess C. Alfred Wegener D. Hammon Hill
what do parables and fables have in common
How do I factor 25x squared - 64
What were some of the human, economic, and political costs of the war?
why do we use y intercept and the slope to graph a line
The part of cell division that causes the separation of the cytoplasmis is