seven people need 90 days to repair and paint a heritage building.if the job should be completed in 15 days.how many more people need to be employed.​

Respuesta :

khababnazir10
khababnazir10 khababnazir10
  • 22-11-2019

Answer:

Here is your answer mate

Step-by-step explanation:

As we know that 7 person take 90 days so 1 person takes 90×7=630 days

As work has to be finished in 15 days than 630/15=42 so

42 people can complete work in 15 days but as we have already 7 people employed so required are

42-7=35 so 35 more are needed

Answer Link

Otras preguntas

how many solution does this problem have? a+5=1/5(15+5a) A. one solution B. more that on solution C. no solution
what is the visual representation of 1/8
find the quotient of 88 and 11
A computer network is best described as two or more computers that are
A blue whale has a length of 28,578 millimeters. What is the length of a blue whale in kilometers? Show your work below by writing the conversion factors you u
solve each equation by taking square roots 2n^2 -8=-33
for the equation x over 3 equals 15 the student found the value of x to be 5 explain the error what is the correct answer
What was one of Portugal’s main goals in exploring the west coast of Africa? A.) to find the northernmost point of the continent B.) to claim territory along
Anoche yo estaba ________ cuando sonó el teléfono. A. leía B. leído C. leída D. leyendo
what is the arc of technology it can't be a brand or app