Resource leveling is a network scheduling technique that seeks to assign nearly equivalent work units to each member of the project team True False

Respuesta :

Emhicee
Emhicee Emhicee
  • 26-01-2020

Answer:

False

Explanation:

Resource leveling in project management is a technique used to ensure that over-allocation of resource or conflicts as a result of over-allocation does not occur.

Cheers

Answer Link

Otras preguntas

Which of the following is a true statement? A. Water breaking apart rocks by freezing and thawing is an example of physical weathering. B. Water moving pieces o
Is this correct ? Please help
How might the speed of a vehicle be determined if its speedometer is broken?
HELPPP - 1 / 4 = - 18 n = ____ ???? HELP
anyone able to help?!
Luis is making quilts for sewing class. He will use 21 yards of yellow fabric, 10.2 yards of green fabric, and 17.3 yards of blue fabric. This amount makes 25
el area de un triangulo de 9cm de altura y su base es desconocida
what does 2 and 1/3 equal? ​
can somebody tell me if this is right or not.
Which of the following is an example of potential energy? 1.The plant sitting on the desk. 2.The person standing up. 3.The airplane flying in the air. 4.The car