The critical path of a network is the A. path with the fewest activities. B. path with the most activities. C. shortest time path through the network. D. longest time path through the network.

Respuesta :

uzamamanzoor1271996 uzamamanzoor1271996
  • 24-02-2020

Answer:

D is correct option

Explanation:

D. longest time path through the network.

The sequence of activities within the network with zero total float is called critical path.

Answer Link

Otras preguntas

A triangle has one angle that measures 59° and one angle that measures 31°. What kind of triangle is it?
While driving on the highway, Dave averages 60 miles per hour. In the city, he averages 30 miles per hour. On a trip to his grandmother's house, Dave drives 2
write a problem that uses a fraction.
A training field is formed by joining a rectangle and two semicircles, as shown below. The rectangle is 98m long and 76m wide. Find the area of the training
ωнαт ιѕ тнє мαιи αяgυмєит тнє вяιтιѕн ℓєαfℓєт υѕєѕ тσ αρρєαℓ тσ gєямαи ѕσℓ∂ιєяѕ
What does the smooth ER do?
True or False: The coordinates of the midpoint of a segment on the coordinate plane are the products of the coordinates of the endpoints of that segment.
What type of ingredients should you avoid eating?
To qualify as a contestant in a race, a runner has to be in the fastest 16% of all applicants. The running times are normally distributed, with a mean of 64 mi
sara buys asweater at a department store.The sweater cost 30 dollars