30men can finish 1/7of a work in 2days.18men will do othe remaining work in ?

Respuesta :

chumxo chumxo
  • 24-09-2016
7/7-1/7=6/7 is the rest of work
1/7 work takes 2days
6*1/7=6/7 work takes 6*2days=12days
30 men takes 12 days to finish the rest of work (6/7)
18 men takes 18*12/30= 7.2days
Answer Link

Otras preguntas

plz help i did it now
toxoplasmosis is an disease that spreads from whom to whom: A. Animal to person B. Person to person
Building a dam to produce hydro-electricity power is one way to take advantage of a common renewable resource. This produces much less pollution than a coal bur
If you knew that the vertical intercept for a straight line was 15, that the slope was -.5, and that the independent variable had a value of 8, the value of the
Which technology keeps track of heart rate during a workout
I can't figure this problem out (6 · r) · 7 =?
There are 5 pairs of socks in one package. Matt buys 3 packages of socks, how many pairs of socks does Matt buy?
can someone help me with this project I need help badly on how to set it up
How do you solve 7 over 20
3 3+(2+12×2)-16÷4 can you also please the work?