Project planning output is :

A. Top-down planning

B. Bottom up planning

C. Waterfall planning

D. Iterative planning

Respuesta :

MubeenAshraf
MubeenAshraf MubeenAshraf
  • 25-12-2021

Answer:

A

Explanation:

The main output of Project palnning is project plan.

Answer Link

Otras preguntas

Schools where coordinated community services are delivered on site are called a. full-service schools b. charter schools c. alternative schools d. primary socia
what right or idea in the preamble do you think is important
After segmentation, the customer group selected by a firm is referred to as the target market. a. True b. False
Read the paragraph below and answer the question that follows. Eric: "Traci, guess what? I came in second in the speech competition!" Traci: "That's great! What
The idea that we are worse off than the individuals with whom we compare ourselves
Please help! I need to pass
c. Compare and contrast driving in the winter and driving in the summer.
Which expressions show the volume and the surface area of this cubed-shaped packing box?
Question 6 Unsaved In South Africa, the President is elected by members of the National Assembly who are elected by the citizens. This means that South Africa
4 && 5 struggling.... little difficult