Two people take 16 hours to clean an auditorium. How long would 8 people take to do the job?

Respuesta :

mcgillt3158
mcgillt3158 mcgillt3158
  • 25-05-2017
it would be 4 hours !!!!
Answer Link
Аноним Аноним
  • 25-05-2017
It should take 8 people about 4 hours to clean an auditorium.

8 people clean 4 times faster than 2 people do (2*4 = 8)

so...

16/4 = 4

hope this helps :)




Answer Link

Otras preguntas

What were the origins of Islam and what are its main beliefs ..
Explain why summer in the Northern Hemisphere is cooler than summer in the Southern Hemisphere.
john and mary went to the mall. Is that a sentence or a fragment?
What were the origins of Islam and what are its main beliefs ..
How many syllable in electricity
(64/9)^(-2/3) Simplify the expression
What were the origins of Islam and what are its main beliefs ..
john and mary went to the mall. Is that a sentence or a fragment?
How many syllable in electricity
(64/9)^(-2/3) Simplify the expression