these are so hard please help me and answer the last 4 I posted

these are so hard please help me and answer the last 4 I posted class=

Respuesta :

Аноним Аноним
  • 23-02-2018
kai:
6 days = 1 shed
1 day = 1/6 shed

Mark:
8 days = 1 shed
1 day = 1/8 shed

Together:
1 day = 1/6 + 1/8 shed 

Ans: 1/6d + 1/8d = 1

Answer Link
carlosego
carlosego carlosego
  • 23-02-2018
The first thing you should know is that the rate of each one is:
 Kaitlyn = 1/6
 Mark = 1/8
 Then,
 d = number of days.
 The equation then if they work together is:
 1 / 6d + 1 / 8d = 1
 answer:
 the equation for number of days it would take to build the sheld together is
 1 / 6d + 1 / 8d = 1
Answer Link

Otras preguntas

The beatles' matching outfits of suit jackets and long ties were likely insisted upon by _______ to give them a more professional look.
Spanish speaking countries in central america
How long did the ancient Olympic Games last?
Which process would be used during the healing process of a paper cut? mitosis, meiosis or differentation
can anyone write me a short corrido about me falling off a hill breaking my arm and going into surgery for 3 days this is due tomorrow and I really need help.
What does consumers willingness to pay depend on?
How many electrons can each orbital hold?
Match the sequence (term) with the correct type of sequence (definition). (4 points) 128, 32, 8, 2, ... Answer 1 1, 3, 9, 27, ... Answer 2 5, 10, 15, 20, ... An
How do you write 137% as a fraction or mixed number in simplest form?
the first picture is the question and the second picture are the answers please help!!